Building time

August 2022 to April 2023

Completed

April 2023

Special challenges

The listed building was reconstructed with particular care, preserving various elements of the old structure, including supports, gable walls, and load-bearing components in the roof area. The planned climate control concept, which provides for a constant room temperaature of 20°C and a humidity level of 50%, was at the heart of all stages of construction.

Client

City of Leipzig

Architects

Pfau Dresden und Architektengesellschaft Peter Zirkel

Building company

Köster GmbH Chemnitz

Products and solutions from SCHWENK

Used:
 6,000 ready-mixed concrete
 Blast-furnace cement CEM III/A 42,5 N
  • BFU Betonförderunion